Given the following information:
Project Requirements (truckloads/week): A needs 45, B needs 50, C needs 20.
Plant Production (truckloads/week): W makes 35, X makes 40, Y makes 40.
Transportation Costs:
To Project A |
To Project B |
To Project C |
|
From Plant W |
$5/truckload |
$10/truckload |
$10/truckload |
From Plant X |
$20/truckload |
$30/truckload |
$20/truckload |
From Plant Y |
$5/truckload |
$8/truckload |
$12/truckload |
Required: Determine the minimum transportation costs for supplying each project.